That:
1. The award of the Leisure Centres Decarbonisation Designs contract to Eddisons to the sum of £1,081,972.25. This sum will cover design through to RIBA 4 (detailed design and technical specification) as well as associated design oversight and quality assurance through the installation and delivery period, to practical completion be approved by the Strategic Director of Environment, Sustainability and Leisure.
2. The associated variation to the scope of works from that noted at Gateway 1, to cover more phases of the project in order to derisk the programme (a variation that occurred based on additional professional advice which the Gateway 1 agreed to seek, and before the tender process took place) be noted and approved by the Strategic Director of Environment, Sustainability and Leisure.