Decision Maker: Strategic Director of Environment, Sustainability and Leisure
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To award the contract to appoint a contractor to undertake retrofit design work on leisure centres
That:
1. The award of the Leisure Centres Decarbonisation Designs contract to Eddisons to the sum of £1,081,972.25. This sum will cover design through to RIBA 4 (detailed design and technical specification) as well as associated design oversight and quality assurance through the installation and delivery period, to practical completion be approved by the Strategic Director of Environment, Sustainability and Leisure.
2. The associated variation to the scope of works from that noted at Gateway 1, to cover more phases of the project in order to derisk the programme (a variation that occurred based on additional professional advice which the Gateway 1 agreed to seek, and before the tender process took place) be noted and approved by the Strategic Director of Environment, Sustainability and Leisure.
Publication date: 22/05/2025
Date of decision: 21/05/2025
Effective from: 31/05/2025