Issue - decisions

GW2 - Fendall & Maltby Strategy for appointment of main contractor

07/10/2025 - GW2 - Fendall & Maltby Strategy for appointment of main contractor

 

1.  That the award for the works contract for the two sites at Fendall Street and Maltby Street to Bloom Construction Group Limited (Bloom) for the sum of £2.67m commencing on the 15 October 2025 for a construction period of 30 weeks to 6 May 2026, be approved.

 

2.  That it be noted that the revised estimated total scheme cost will be £17m including on costs, £2m above the existing budget for this scheme.

 

3.  That it be noted that there is a performance bond in relation to the original works contract with ARJ Construction Limited of £1.3m to call upon on completion of the project, as set out in the Gateway 1 report.