Issue - decisions

Gateway 3 – Cost Variation Decision - Temporary Accommodation – Contract 3

23/05/2023 - Gateway 3 – Cost Variation Decision Temporary Accommodation – Contract 3

That the Strategic Director of Housing:

 

1.  Formalises his pervious approval to the variation of theTemporary Accommodation Contract 3, refurbishment/conversion contract with Niblock (Builders) Limited (Niblock) at an additional cost of £593,073 varying the contract sum from £1,869,695 to £2,462,768.

 

2.  Approves a variation to the contingency for the above contract, increasing the sum by £29,653 varying the contingency from £93,485 to £123,138.

 

3.  Notes the increase to the estimated other on-costs, including 4% development allowance associated with the contract, from £246,278 to £481,261 resulting in a variance of £234,983.

 

4.  Notes the increase of the total scheme costs from £2,209,458 to £3,067,167 with a variance of £857,709.

 

5.  Notes that this report was considered at the Departmental Contracts Review Board (DCRB) in July 2022 and was not sent for approval until April 2023.