RESOLVED:
1. That the progress and next steps relating to works at Marie Curie House, delivering on the recommendations of the independent review, and reviewing the works undertaken at Lakanal to review whether any additional works to Marie Curie are required at Lakanal be noted.
2. That officers are instructed to bring a further update on these during September 2023.
3. That it be noted that the council will not use qualitative design reviews (QDRs) for other existing buildings.