Issue - decisions

GW3 Approval of Commercial Way contract cost increase

17/06/2021 - GW3 Approval of Commercial Way contract cost increase

 

 

1.  That the variation to Commercial Way new build contract with Durkan Limited (Durkan) at an additional scheme cost of £4,836,486 be approved.

 

2.  That it be inclusive of a variation to the contingency for the above contract to maintain a 5% build contingency.

 

3.  That the reduction of £1,026,762 in the estimated on-costs associated with the contract be noted.

 

4.  That the revised anticipated contract completion date of December 2023 be noted.