Note: This is an executive function for decision by the multi-ward forum.
RESOLVED:
1. That the reallocation of underspent funds of £10,095 carried forward from previous years underspend, be agreed.
2. That the following allocation of funds for the 2024-2025 Devolved Highways budget in the North West multi-ward area be agreed:
ST GEORGES
Reference |
Title |
Amount |
2092544 |
Bike Hangar Austral Street |
£5,000 |
BOROUGH & BANKSIDE
Reference |
Title |
Amount |
2102007 |
Greener, quieter, walkable Webber Street |
£10,000 |
2103112 |
Wallis Alley Improvement |
£21,000 |
2103122 |
Improving Bike Parking on Holland Street |
£5,000 |
CHAUCER
Reference |
Title |
Amount |
2085372 |
Swan Street Speed Bump |
£8,000 |
2074638 |
Tabard St bike stands |
£2,800 |
|
Streets for People priority projects incl. bike hangars (to be confirmed once consultation closes) |
£18,000 |
|
Roebuck Piazza – improving cycle/pedestrian safety |
£8,000 |
2102934 |
Bartholomew Street Trees |
£10,000 |
LONDON BRIDGE & WEST BERMONDSEY
Reference |
Title |
Amount |
|
Streets for people’s priorities |
£38,095 |
Note: This is an executive function for decision by the multi-ward forum.
The chair announced that there was £100,476 in additional funding from previous years underspend, current programme underspend and current programme project cancelations. In addition to this, there was £139,681 available for the 2022-2023 Devolved Highways programme for new projects in the North West multi-ward area.
RESOLVED:
1. That the reallocation of underspent funds carried forward from previous years’ underspend, current programme underspend and current programme project cancelations be agreed.
2. That the allocation of funds for the 2022-2023 Devolved Highways capital programme in the North West Multi Ward area from the list of applications set out in appendix 1 be approved.
Borough & Bankside
Reference |
Title |
Amount |
1747023 |
Valentine Place |
£5,000 |
|
Toulmin Street |
£61,190 |
1740193 |
Greening Flat Iron Square |
£10,000 |
Total |
£76,190 |
Chaucer
Reference |
Title |
Amount |
|
4x Chaucer EVCPs |
£14,000 |
|
Tabard Square Improvements |
£36,080 |
Total |
£50,080 |
London Bridge & West Bermondsey
Reference |
Title |
Amount |
1746695 |
Tanner Street Greening and Safety (Investigation) |
£28,000 |
|
Highway Minor Repairs and Street Furniture |
£35,095 |
Total |
£63,095 |
St George’s
Reference |
Title |
Amount |
Gladstone Street/Coinbrook Street Footways |
£50,792 |
|
Total |
£50,792 |
Note: This is an executive function for decision by the multi-ward forum.
RESOLVED:
1. Approves the reallocation of underspent funds carried forward from previous years underspend, current programme underspend and current programme project cancellations
2. Approves the allocation of funds for the 2022-23 Devolved Highways capital programme in the South Multi Ward Area from the list of applications set out in Appendix 1.
CHAMPION HILL
Reference |
Title |
Amount |
1739703 |
Ivanhoe, Avondale, Malfort Junction Improvement |
£25,396 |
DULWICH HILL
Reference |
Title |
Amount |
1736361 |
Lordship Lane safe crossing |
£28,792 |
DULWICH WOOD
Reference |
Title |
Amount |
1739683 |
Traffic Calming in Little Bornes |
£10,000 |
1743124 |
Dulwich Wood safer streets |
£24,740 |
|
Colby Road speed hump |
£10,764 |
1734396 |
Farquhar Road speed calming |
£19,682 |
DULWICH VILLAGE
Reference |
Title |
Amount |
1740389 |
5 ways proposals Half Moon Lane |
£6,500 |
1741584 |
Dulwich Village secure cycle parking |
£1,250 |
500088 |
6 Magnolia Trees for Casino Avenue |
£12,000 |
|
Dulwich Village Cycle Hangars |
£9,446 |
GOOSE GREEN
Reference |
Title |
Amount |
1741274 |
e-Cargo bike locker Lordship Lane/North Cross Road |
£2,800 |
1746541 |
Blackwater Street Tree Pits |
£10,560 |
1740860 |
Electric Charging Points Goose Green (including Hinckley Road) |
£24,735 |