Issue - decisions

Gateway 2 approval to the appointment of the demolition contractor for phase 2 of The Charter School East Dulwich project

08/09/2020 - Gateway 2 approval to the appointment of the demolition contractor for phase 2 of The Charter School East Dulwich project

 

1.  That the award of the demolition and enabling contract for phase 2 of The Charter School East Dulwich project to John F Hunt Regeneration Limited in the sum of £1,589,524 consisting of £676,690 plus a provisional sum not to exceed £912,834 for asbestos removal costs be approved.

 

2.  That a project contingency sum of £122,476 to meet any unforeseen costs be approved. This sum is the difference between the £1.712m approved at GW1 stage and £1,589,524.

 

3.  That the decision to approve any spend against the project contingency sum be delegated to the Director of Education.