Issue - decisions

Gateway 2 - Award for Preconstruction Services Abbeyfield Estate HINE (Maydew House) works

17/06/2020 - Gateway 2 - Award for Preconstruction Services Abbeyfield Estate HINE (Maydew House) works

RESOLVED:

 

1.  That the award of the pre-construction services for Abbeyfield Estate High Investment Need Estate (Maydew House) works to Bouygues UK Ltd for a period of 12 weeks from July 2020 be approved.

 

2.  That it be noted that a separate gateway 2 report will be presented in autumn 2020 for the award of the main works contract which is highly likely to be the same contractor as detailed in paragraphs 18-19 of the report.