Policy and Resources Strategy: capital monitoring report outturn 2017-18 and capital programme refresh 2018-19

25/07/2018 - Outturn Capital Monitoring for 2017-18 and Capital Programme Refresh for 2018-19 to 2026-27

RESOLVED:

 

1.  That it be noted that a refresh of the ten-year capital strategy and capital programme will be presented to council assembly in quarter 1 2019, following cabinet approval.

 

2.  That the virements and variations to the general fund and housing investment capital programme as detailed in Appendix C of the report be approved.

 

3.  That the inclusion in the programme of the capital bids set out in Appendix E of the report be approved.

 

4.  That the outturn and resources for 2017-18 and future years for both the general fund and housing investment programmes as detailed in Appendices A, B and D of the report be noted.

 

5.  That the resulting general fund capital programme for the period 2017-18 to 2026-27 as at year-end, as detailed in Appendices A and D of the report be noted.

 

6.  That the substantial funding requirement of £264m for future years which needs to be identified for the general fund programme in order for this to be fully delivered, as summarised in Appendix A of the report be noted.

 

7.  That the resulting housing investment programme for the period 2017-18 to 2026-27, as detailed in Appendix B of the report be noted.

 

8.  That the significant funding requirement of £308m which needs to be identified for the housing investment programme to be fully delivered over the remaining term of the programme, as detailed in Appendix B of the report be noted.