Issue - decisions

Gateway 2 - Contract Award Construction of new build units at Daniels Road

20/03/2018 - Gateway 2 - Contract Award Construction of new build units at Daniels Road

1.  That the award of the works contract for Daniels Road to Geoffrey Osborne Limited in the sum of £4,498,007 and an additional contingency sum of £324,900 which produces a total cost of £5,792,310 from 4 June 2018 for a period of 58 weeks plus 12 weeks for mobilisation be approved.

 

2.  That the project’s associated on costs of £969, 401 be noted.