Issue - decisions

Gateway 2: Contract award approval - Sumner Road Block B works

23/11/2016 - Gateway 2: Contract award approval - Sumner Road Block B works

1.  That the award of the main works contract for the general needs housing at 80 Sumner Road (also known as Sumner Road B) SE15 to Morgan Sindall Construction and Infrastructure Ltd. in the fixed sum of £9,713,467 for a contract period of 74 calendar weeks commencing on 1 December 2016, be approved.

 

2.  That a client-held contingency which will only be expended through a formal change order process against unforeseen risks, which will be approved through a separate Gateway 3 report, be noted.

 

3.  That the award is subject to final clearance of the contractor’s proposals by the Strategic Director for Housing and Modernisation be noted.