Elephant and Castle regeneration progress report

23/07/2014 - Elephant and Castle Regeneration Progress

RESOLVED:

 

1.  That the regeneration agreement dated 23 July 2010 between the London Borough of Southwark and Lend Lease (Elephant & Castle) Limited be amended as follows:

 

(a)  the transfer of the Crossways Church site is delayed until the earlier of the completion of the replacement Crossways Church at Hampton Street or 30 September 2016.

 

(b)  to revise MUSCO provisions with the sustainable energy provisions provided within the Planning Committee approval (minute 6) on 15 January 2013.

 

2.  That it be confirmed that the land edged black on the plan at Appendix B of the report that is currently held for housing and leisure purposes is no longer required for those purposes and the appropriation of the land to planning purposes be confirmed to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972

 

3.  That it be confirmed that the land edged black on the plan at Appendix D of the report that is currently held for housing purposes is no longer required for those purposes and that the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 be approved.