Issue - decisions

Gateway 2: Contract Award Approval for the Design and Build of Southwark Park Primary School

18/03/2013 - Gateway 2: Contract Award Approval for the Design and Build of Southwark Park Primary School

1.  That  the award of the contracts outlined in table 1 of this report, for Southwark Park Primary School to 4 Futures Limited, the council’s Local Education Partner (LEP), subject to:

 

  • The financial implications for the council being no more than the value disclosed in the closed version of this report;
  • Confirmation from the council’s Technical Advisor that the project represents value for money (in line with the agreed value for money protocol);
  • The submission from the LEP satisfying the council’s requirements.

 

is approved; and

 

2.  That the contract will not be awarded to the LEP should the requirements listed in paragraph 1 not be met is approved