Gateway 2: Aylesbury Estate - Replacement of underground secondary heating pipe work, emanating from Latimer plant room

11/03/2015 - Gateway 2: Aylesbury Estate - Replacement of underground secondary heating pipe work, emanating from Latimer plant room

 

1.  That prior approval for the procurement strategy outlined in the report seeking exemption from Contract Standing Orders (CSO) as provided in CSO 4.9 be formalised.

 

2.  That prior approval for the award of the Aylesbury Estate, estate wide underground heating mains replacement 2013/14 (emergency works) via an order placed under the individual district heating contact with T Brown Group Ltd on 31 July 2013 in the sum of £3,220, 800 for a period of 52 weeks be formalised.