Agenda item

REVIEW OF THE CURRENT CHALLENGES AND CONTEXT AROUND HOUSING DELIVERY

To hear from officers and from representatives of the Council’s developer partners on the current context around and approaches to housebuilding and wider development.

Minutes:

The Chair introduced the item, explaining that the opportunity to hear directly from Officers, the Cabinet Member and especially partner-developers would inform and enable the Commission to hold Cabinet to account regarding its housing delivery targets. In turn, this means the Commission’s recommendations to be published at the end of the Municipal year should be better informed.

 

The Chair also made a general note to the public, clarifying how the Commission works namely as a body making recommendations to Cabinet rather than making decisions itself. It is for Cabinet to adopt or reject the recommendations.

 

The Chair then invited Officers (Stephen Platts, Director of Planning and Growth, Colin Wilson, Assistant Director for Strategic Developments, and Cameron Radford, Senior Planner) and the Cabinet Member for New Homes and Sustainable Development (Councillor Helen Dennis) to speak to the Commission and provide some context around housing delivery in Southwark before the Council’s developer-partners focused on specifics.

 

Steve (Stephen Platts) began by describing London’s housing delivery crisis, referencing the slides streamed on screen for the Commission and public.

 

Steve noted that:

 

  • housing delivery in London was at its lowest since records began
  • a central constraint is viability (i.e. profitability) at a level sufficient to attract capital compared to alternative investments (e.g. bonds, equities). Without returns commensurate to risk, residential development becomes less attractive to lenders as an investment choice
  • further pressures included the collapse in international investment, reduced domestic investment, lack of affordability for buyers, Housing Associations diverting capital away from Section 106 acquisitions towards maintaining existing stock to meet regulatory requirements (in turn increasing risk for developers)
  • nationally, there may be issues with the planning system slowing development but, in Southwark, this was not the case

 

 

Colin then provided further historical and technical background, informing the Commission that:

 

  • targets around social housing delivery would be difficult to meet without the levels of investment seen in the postwar period up to circa 1979
  • earlier policies such as the 2012 NPPF shifted social rent completions to “affordable” rent, driving growth in the housing waiting list and the need for Temporary Accommodation
  • with reduced grants and delivery increasingly dependent on Section 106 contributions, dependence on developers and market conditions had increased
  • build costs have increased 44% since 2016 whilst growth in flat prices increased only 4%
  • increased regulation of, for example, thermal efficiency and safety was important but in a context where regulatory control lacked capacity, the time required for revenue to flow to investments increased by 50%
  • viability for first time buyers had decreased (the average income required in 2015 was £68k but £103k by 2025)
  • the regulatory regime around student and co-living housing is less demanding than that for private housing, enabling developers of the former to outbid private housing developers in competition for limited sites (although uniquely in London, Southwark also ensures private housing is delivered in student- and co-housing schemes)

 

Steve then focused on housing delivery in Southwark, observing that:

 

  • Elephant and Castle accounted for the greatest number of approvals although over time it was expected that the relative importance of the Old Kent Road area would increase
  • approvals had still met the 35% Affordable target (10% Intermediate + 25% Social Rent) but this was becoming harder to meet give the context described above

 

Councillor Dennis then explored recent planning developments noting that:

 

  • the Council’s strong focus on Social Rent had meant that, as reported in the GLA’s most recent statistics, Southwark had the highest number of social rent completions and the second highest for social rent starts
  • the affordable housing made possible through student- and co-housing would still be possible while fast-track planning was being promoted centrally
  • in spite of a range of challenges described above, the Council was still committed to its social housing delivery

 

In response to questions from Commission members, Officers and the Cabinet Member noted:

 

  • that Co-living and student housing developments had not been a particular objective of the Council but it had had its hand forced to consider these and, with student housing, whilst there were broader policy outcome concerns (e.g. falls in international student numbers), student housing remained undersupplied in London
  • the challenges around delivery were felt particularly strongly in London relative to the rest of the country – for example, in terms of higher build costs in London but also that high-rise, private developments were more likely in London and these were also the type of building subject to the regulatory controls and delays discussed earlier
  • that the potential issue of Section 106 funding being used by for-profit Housing Associations has been noted by the Council especially where, for example, those with highest housing needs including, potentially, complex medical needs are being supported and the Council was working to promote the sharing of best practice across providers

 

The Chair then thanked officers and the Cabinet Member, and invited the Council’s partner-developers to speak to the Commission. Richard Palmer (Development Director at Delancey), Oli Campbell (Managing Director, Bouygues Development) and Jamie Hunter (Development Director, The Hill Group) came forward and presented in the order given.

 

Richard Palmer started by noting how refreshing it was to hear the challenges around development acknowledged and detailed as they had been.

 

Richard then introduced his work (leading development at the Elephant and Castle for Delancey, a significant developer in the UK with particular focus on London).

 

For the kind of large-scale developments under discussion, Richard agreed with Steve and Colin’s earlier points that the large and long-term capital investments driving development required stable returns to appeal to international investors. Without these, those investors would divert their capital elsewhere – a process which Richard noted is happening and which simpler processes with fewer blockers would instead encourage more stable returns.

 

Richard spoke of London’s housing crisis, noting that to achieve the government’s target of 1.5million homes over this parliament, London would need to deliver 88,000, higher than the London Plan’s 52,000.

 

Richard then identified what he thought contributed to the crisis as a “perfect storm” including external factors such as the war in Ukraine in addition to the main construction and legislative environments (build cost inflation, cost of finance, the Building Safety Act etc). He also noted that many of these features were, per se, laudable (e.g. increased safety standards, dual aspect and cycle storage) but their combined impact was, nevertheless, to increase development risks and investment costs.

 

Richard then closed by suggesting potential solutions, including:

  • increased national government support
  • additional resource to the Building Safety Regulator
  • an extension of emergency measures to help get development going
  • relaxation of certain design standards

 

Next, Oli Campbell introduced Bouygues Development’s work for Southwark: on the Tustin Estate; a project for Key Workers and redevelopment of LSE’s Bankside site.

 

Oli commented on the breadth of the officer presentation and picked up on the question of financing, adding further detail. Here, he noted that as a key metric of the financial markets, 10 Year Gilts, contributed to the pricing of private and Housing Association capital. Recent significant movement in bond prices have affected what developers can and can’t do. The net effect is that developers have taken more guarded, conservative approaches to new projects.

 

Oli also spoke about the supply of land, noting that buyers had sometimes failed to develop land because of higher financing costs coupled with drop in demand. As well as slowing transactions, this also means that owners of land can exercise their option to wait until the development climate improves, hindering the challenge around housing.

 

In the case of public land, changes to Masterplans can make them unviable and/or, politically, increase the need for consultation with residents. Whilst important parts of local democracy, these changes and assurance can affect the costs and risks which developers have to bear.

 

In addition to increasing construction costs, Oli also noted the increased fragility of the supply chain. For larger developers, this has driven them to be much more cautious around who they sub-contract to. A knock-on effect is important: with activity decreasing alongside a fragile supply chain, skills can be under threat.

 

Oli then spoke about two aspects of how building safety affects housing delivery. First, in terms of viability, the requirement for two staircases has increased what needs to be built relative to what can be sold with clear effect on viability. Second, the extra time, costs and risks required in producing Stage 4 design pushes back even more the time at which revenue can start to flow to the developer. This extra cost and risk can more easily be absorbed by larger developers and is likely to have a higher impact on SMEs.

 

Lastly, in relation to affordable homes and drawing on the Making Social Rent Homes Viable paper, Oli made the point that, in his view, the cross-subsidy model wouldn’t work and that what was needed was increased direct subsidies to fund housing.

 

Jamie Hunter then spoke of The Hill Group’s work as the 2nd largest privately owned housebuilder in the UK, often working in joint venture with local councils and housing associations. In Southwark, The Hill Group has worked with the Council to deliver 900 homes.

 

Jamie referenced earlier discussion around the importance of the supply chain, noting their work in supporting and sustaining the development of skills and of SMEs themselves.

 

Jamie also highlighted the role of supply chains in viability, noting that in his view, where supply chains were carefully managed and working, prices were beginning to come down.

 

Jamie identified two ways to reduce development costs (in addition to those already made): first, through involving partners early in the design process; second, where relevant, considering the use of modular construction.

 

Jamie closed by proposing the increased use of public-private investment partnerships where both parties jointly invest. As a model which sits outside public procurement, it can, in his view, be a useful model for delivering quickly where values and outcomes are aligned.

 

Commission members then asked questions of the developer-partners with responses noting:

 

  • that land-purchasing strategies varied and included purchasing with options, purchasing conditional on planning consent included and, occasionally, sales for zero land value with mechanisms then for limiting developer profits
  • that viable schemes which included all planned affordable housing was ideal but when viability would not be achieved, it was helpful to have alignment around the outcomes all parties would work towards
  • profitability fluctuated as when construction cost inflation reached 5-6%, reducing profits accordingly, the risk had to be borne by developers
  • that to support the demand side and help to make housing more affordable, one additional strategy to those mentioned included Build to Rent
  • that Shared Ownership was a useful option in a wider “menu”, providing a step onto the housing ladder as long as there was clarity and fairness around service charges
  • that the value of relaxing design standards to aid delivery was debatable
  • that while new safety requirements were creating difficulties, they were recognised as valuable
  • the value of developing skills and creating the conditions for employment, especially for young people was key – as well as facilitating apprenticeships, Section 106 funding could provide a way to retain and continue developing young people’s skills as could a more explicit focus on social value by all parties in the supply chain
  • the recommendations they would make to increase housing delivery include decreasing the time taken to get Section 106’s signed, decreasing political involvement in the planning process (e.g. where an officer recommends approval, this should stand – with Members therefore “YIMBYs” by default), innovate new routes to partnership delivery, use early involvement of a preferred bidder to combine the Council’s land and knowledge of resident needs with the developer’s know-how and resource

 

The Chair thanked the developers for their contributions.

 

Supporting documents: