To approve the release of £1,752,478.34 from the agreements listed in Appendix 1 of the report, in order to contribute to the overall capital programme requirement for the seven schools listed in the report.
Minutes:
Alistair Huggett, Planning Projects Manager introduced the report.
RESOLVED:
That the release of £1,752,478.34 from agreements listed in Appendix 1 of the report, in order to contribute to the overall capital programme requirement for the seven schools listed below, the total lifetime cost of which is £80,610,920 be approved.
School |
Total Available (£) |
Crawford Primary School |
315,666.20 |
Phoenix Primary School |
305,490.51 |
Charles Dickens Primary School |
249,751.67 |
Robert Browning Primary School |
408,880.22 |
Bellenden Primary School |
30,556.00 |
Cherry Garden Special School |
419,206.03 |
The Charter School East Dulwich |
22,927.71 |
TOTAL |
1,752,478.34 |