To update members on the progress for highway schemes in the Dulwich area.
Minutes:
Members noted the information below which was the current status of the highways programme for 2013 -2014 for the Dulwich community council area.
Note: This item is an executive function.
Scheme Name
|
Community Council |
Ward |
Allocation |
Carriageway /Footway |
Status
|
Dulwich Village |
Dulwich |
Village |
£16,302 |
Footway |
Completed
|
Dulwich Village |
Dulwich |
Village |
£17,623 |
Footway |
Completed
|
Dulwich Village
|
Dulwich
|
Village
|
£11,763
|
Footway
|
Completed by 25 Feb 2014
|
Colby Road
|
Dulwich
|
College
|
£49,728
|
Footway
|
Programmed for 17 March 2014
|
Goodrich Road to Barry and Upland Roads
|
Dulwich
|
East Dulwich
|
£42,980
|
Carriageway
|
Programmed for 6 March 2014
|
Pellatt Road
|
Dulwich
|
East Dulwich
|
£22,980
|
Carriageway
|
Programmed for 10 March 2014
|