Canada Water Library - Update and Financial Position

(Papers to follow.)

Minutes:

5.1   Cllr Paul Noblet excused himself for this item because he was a former executive member (Cabinet lead) with responsibility for this area.  The Chair invited Canada Water Project Director, Tim Thompson, to present on building the Library.

 

5.2  The Project Director explained that the Library was a key part of a large regeneration masterplan for Canada Water. This masterplan had come out of Southwark Council identifying back in 2001 that there were opportunities to develop the area because of significant land holdings and the arrival of a new transport infrastructure. The area had suffered from significant post industrial decline since the 1970’s.

 

5.3  The council ran an EU procurement process and by 2003 was in negotiation with British Land Canada Water Quays (BLCWQ) – as special purpose vehicle - as the preferred development partner.

 

5.4  BLCWQ had a team leading the project and this included architects and quantity surveyors. They brought forward the master plan and further engaged with stakeholders, including conducting significant community engagement.

 

5.5  This resulted in a planning proposal for the public realm projects scheduled for sites A and B of the Canada water masterplan; including detailed proposals for the Library and Plaza, and less detailed proposals for housing and other developments. Planning approval was given.

 

5.6  The consultant team then became the responsibility of the council and the team underwent some changes to the team responsible for the construction project.

 

5.7  The construction contract was awarded to ISG Jackson and in June 2009 the construction of the Canada Water Library commenced on site.

 

5.8  The project encountered some early problems with the substructure. This is a complex project and the floor combines the tube entrance. This substructure blockage caused 14 weeks prolongation. Since then the officer reported that there have been no holdups. The skeleton structure is taking shape and all the floors are nearing completion, and the roof will shortly follow.

 

5.9  Construction is due to be finished by the end of June 2011, with the public accessing the library by August, ready for a September official opening. The Library is a headline project offering library services, increased study and meeting space as well as very high standards of accessibility.

 

5.10Adrian Whittle, Head of Culture libraries, learning and leisure, then gave an update on plans for the new library. He explained that the vision is for a place centred on adult and community learning with increased opportunities for cultural access. There will be lots of opportunities for adult and family learning and a programme of activities for young people aged 0 – 20 years.  The service wants the library to be a hub for the existing communities. The venue is anticipated to be a one stop shop for learning, with social spaces throughout.

 

5.11Family provision is very good with baby changing facilities. Alongside this there are high standards of access for disabled people, with lifts, toilets and an adult changing area, a first for Southwark Council buildings.

 

5.12This is green building making extensive use of IT, including free access to internet Wi-Fi in the library and plaza.

 

5.13The Head of libraries reported that there had been lots of learning from Peckham Library and libraries around the country. Rotherhithe is old and poorly located and this library will be closed once the new library opens. There is also the option of closing this library early to save money.

 

5.14BEC are based there. Officers have asked them to consider using the new library to continue providing their services as we would like a mixed economy of providers.

 

5.15The Chair thanked the speakers and invited members to question officers, and initiated discussions by posing a number of questions. The Chair drew attention to point 14 of the tabled report,  which details how the Executive approved the sums of £8.5m and £5.6m at the meetings on 13th February 2007 and 21st October 2008, respectively, making £14.1m in total. He stated he was particularly interested in how the council moved from £8.5 million to over £14 million. The Project Director responded that although Southwark was part of the steering group at the time the forecast was made that the library would cost £8.5 m to construct, the council  was not directly managing the project. The quantity surveyors made errors in estimating the costs. In the run up to the planning stage officers had concerns. When the consultancy team moved in house they moved under the council’s direct control and changes were made to the personal.

 

5.16The Project Director went on to explain that originally the council was targeting early 2010 for completion. The library was one aspect of an overall master plan leading to a complex deal taking place in a very difficult economic climate.  The development site was chosen for sound urban design reasons; located near the tube and close to areas suitable for high density housing. The library drove up the land value because it made the area more desirable, generating high level capital receipts for the council. Some of this is being ploughed back into this phase of the library. The tenders that came back were in the high range, however the quality of this project sets the tone for future regeneration and this enables us to generate financial benefits for Southwark

 

5.17A member requested more explanation on the ‘Value Engineering’ requirement? The Project Director explained that during the tender stage there was a list of items identified that money could be saved on and these totalled £1million. We are working with the design team to crystallise all the construction savings.

 

 

5.18A member asked about ongoing risk to the budget. The Project Director stated that from the outset the biggest potential risk was indentified to be the substructure, and that has now been resolved.

 

5.19Members asked at what point the council could have pulled out. The Project Director explained that the library was a key part of the urban design and wider regeneration project, and this would have made it difficult to pull out of without jeopardising the wider deal and severely impacting on timetables.

 

5.20A member asked how confident and comfortable are you that this variance is at its largest? Could the project lead to additional costs that the council would find it hard to cover? How confident are you that costs would not raise further? The Project Director responded that he while he could not give a guarantee because the nature of the project means that it is technically challenging he believes that they are beyond the major risk. He assured members they are proactively managing the construction and there are elements that officers will be looking at for financial change.

 

5.21A member asked if the library had been scrutinised before. Shelly Burke, Head of Scrutiny, responded that there had been a couple of questions posed under ‘executive questions’ but no specific review.

 

5.22There was a query from a member asking if the council could claim compensation for errors in the quantity surveyor’s estimate?  The officer responded that this is very difficult to prove as the threshold is high; the council would need to prove negligence and financial loss. The other option would have been to go back to the drawing board and ask the architects to submit a new design, but the knock on effects would have been high as it would have affected the masterplan and tendering. A member asked if the legal route of pursuing compensation was still an option.  The Project Director responded that there are financial risks associated with legal action, a substantial case would need to be established, and however we have not closed this door.

 

5.23Members enquired if the costs can be contained and requested reassurance that the figures will be kept within the projections. The Project Director replied that we have significant project management tools in place, and significant team expertise. Moreover the biggest risks were underground and we have now overcome these.

 

5.24The Chair made strong recommendations that the project keep within budget and that it opens on time.

 

5.25Members moved on to considering the revenue costs and enquired whether the annual running costs of £1.1 million offered a gold plated service or if this is a reasonable amount?  Clarification was requested on the number of librarians employed at the new library and also the number currently employed at the Rotherhithe library?

 

5.26The Head of libraries confirmed that there are 4.5 full-time equivalent staff employed at the old library. The new library will employ 32 full time equivalent staff across the week. Savings have been made by increasing self service options. All but 2 would be front line staff.

 

5.27Officers were asked about the recruitment timetable. The Head of libraries stated that the Library manager and Programme and events manager would be the two initial posts that would be recruited. He also stated that these are reasonable costs and that repairs and maintenance had been budgeted for early.

 

5.28There was a query on the library revenue budget and an explanation was requested for item ‘NNDR’? It was explained that these were non domestic rates.

 

5.29The Chair asked if you had to make 10% cuts what would you do. He further asked if you would consider reducing opening hours. The officer advised that options for savings would be brought to members. He confirmed that reducing opening hours could be amongst these but pointed out that this also reduces the opportunity to generate income and saves little on running costs. Officers are also looking to maximise income from the cafe and have been approached by a number of high street providers, but would not like to exclude local providers.

 

5.30There was a query about competition and undermining the plaza shops and cafes. The officer responded that the library, plaza and retail units have always been seen as complementary to give the centre a buzz.

 

5.31A member asked if the committee could do some modelling to look at how the space could be used by the community. The Project director explained that some of the site comes to us for community use for a peppercorn rent. We have been considering how much space should be allocated for commercial use, given the amount offered by the library and plaza and whether this should be offered up for commercial use to increase commercial yield.  The officer advised members to bear in mind that this is a mature design so changes to the physical structure would probably add costs. 

 

5.32The Project Director said that there are place making opportunities and welcomed a visit by the committee members to view and visit the library and plaza.  This was agreed by members. Furthermore it was agreed that this would help with planning out further work. Members would undertake the visit and then meet to scope out the work and advise officers of further documentation that would help their review.

 

5.33A member commented that she would like to give consideration to how organisations such as Learn Direct could contribute to the delivery of the library services.

 

5.34Cllr Livingstone commented that there are massive financial challenges facing the council and we could be looking at 25% cuts. He reported that he will need to justify these costs and consider knock on effects; an example of this might be the community libraries.

 

5.35A member commented that he understood that the library will have a positive effect on wider land values and it would be good for scrutiny to look at the evidence for this. The Project Director commented that the financial gains will be generated on the capital side, rather than increasing revenue – in terms of being a beacon to regenerate the area.

 

RESOLVED

 

The minutes from this meeting will go to the cabinet.

 

A site visit will be arranged for the committee to tour the library and plaza with the Project Director and Head of Culture libraries, learning and leisure. The Scrutiny Officer will contact members of the Committee with a suitable date.