8 Proposed Amendment to Interim Outline Business Case for Aylesbury Estate Private Finance Initiative
To seek agreement to amend the scope of its Outline Business Case (OBC) under the Government Private Finance Initiative (PFI) to include sites 1b & 1c as well as those in Phases 2 & 3 and to request officers to consult with affected local residents to obtain their views on possible changes to the phasing and timing of the Aylesbury regeneration programme.
Supporting documents:
Minutes:
RESOLVED:
1. That the scope of the Outline Business Case (OBC) under the Government Private Finance Initiative (PFI) be amended to include sites 1b & 1c as well as those in Phases 2 & 3.
2. That officers consult with affected local residents to obtain their views on possible changes to the phasing and timing of the Aylesbury regeneration programme.