11 Gateway 3 - Ledbury Estate Renewal Section 8-12 Approval (Phase 2)
To approve Phase 2 of Ledbury
Estate Renewal Section 8-12
Supporting documents:
Minutes:
RESOLVED:
That
the following recommendations be approved:
That the Executive;
- Approves the variation of the Ledbury Estate Regeneration
Contract with Higgins Partnerships 1961 PLC (Higgins) by a total of
£35,375,849, from a current contract value of
£179,960,999, to a revised contract sum of £215,336,848
(see paragraphs ?90 to
?106 for details) in
order to meet both contractually required inflationary uplifts and
comply with legal requirements as mandated by the Building Safety
Act 2022.
- Approves the use of £36,950,000 time-limited Right to Buy
receipts to fund the works costs for the 65 originally designated
private sale homes (20 in Phase 1 and 45 in Phase 2) to become
council homes for social rent (see paragraphs ?90 to ?106 of the report for details).
- Approves several additional variations, including changes in
sequencing, changes required to meet building safety regulations
and updates to drawing and tenure schedules underpinning the
contract as outlined in paragraphs ?42 to ?42.5 of the report.
- Approves, subject to approval of Recommendation ?2, a minor revision to the
approved Local Lettings Plan to account for the additional 65
council homes for social rent that will be allocated in accordance
with the other council homes for social rent (see paragraphs
?120 to ?122 of the report).
That the following recommendations be noted:
That the Executive;
- Notes
that by Approving Recommendation ?2, the overall impact on debt to the
HRA is reduced as outlined within the closed report as well as
delivering a range of financial and non-financial benefits as
outlined between paragraphs ?98.1 to ?98.5.
- Notes
the increased grant from the Greater London Authority for all of
the originally designated council homes for social rent delivered
in Phase 2, being 215, by an additional grant allocation of up to
£27,875,000, comprising £26,875,000 from the enhanced
grant rate for 215 Phase 2 social rented homes and £1,000,000
already approved for four phase 1 homes converted from shared
equity to social rent as set out in paragraphs ?108 to ?115 of the
report.
- Notes
that by approving Recommendation ??1, the Executive is approving the
start of the main construction works for Phase 2 of the Ledbury
Estate Renewal by choosing not to enact the second and final
unilateral break clause contained within the Ledbury Estate
Regeneration Contract with Higgins.
- Notes
the anticipated Start on Site date of October 2026 for Phase 2 and
associated benefits as outlined in paragraphs ?35 to ?37 of the
report.
- Notes
that variation to contract will be undertaken via a Deed of
Variation which will vary the Ledbury Estate Regeneration Contract
in line with Recommendations ?1 and ?3.