19 Gateway 3 – Variation Decision: Phase 2 of Extension to the South East London Combined Heat and Power plant (SELCHP) Heat Network
To approve the proposed variation to the council’s heat supply agreement.
Supporting documents:
Minutes:
Councillors Evelyn Akoto and Natasha Ennin, having declared a disclosable pecuniary interest in respect this item, did not participate in the discussion on this item.
RESOLVED:
That, subject to receipt of First Tier Property Tribunal dispensation (see paragraph 2 of the report), and approval of the community infrastructure levy funding and green building fund funding (see paragraph 3 of the report):
1. That the proposed variation to the council’s heat supply agreement with Veolia ES Southwark Limited (VESS) involving works which requires capital expenditure from the council of £5,500,000 and the supply of low carbon heat to 31 March 2050 at an estimated cost of £208,761,745 (precise value will depend on inflation) making a total estimated variation value of £214,261,745 and a total estimated contract value of £267,873,179 be approved.
3. That for the council’s £5,500,000 capital contribution to receive separate approval (£2,000,000 from the green buildings fund, £1,000,000 of which is subject to a drawdown request to the planning committee, and £3,500,000 from the strategic community infrastructure levy requiring approval by the cabinet, also at December 2025 cabinet meeting but falling within a separate report) be noted.