17 Gateway 1 - Procurement Strategy Approval Abbeyfield Estate HINE (Maydew House)
To approve the revised procurement strategy for the use of the GLA’s London Development Panel framework to procure development partners for the Abbeyfield Estate, High Investment Needs Estate (HINE) (Maydew House).
Supporting documents:
Minutes:
RESOLVED:
1. That the revised procurement strategy for the use of the GLA’s London Development Panel framework to procure development partners for the Abbeyfield Estate High Investment Needs Estate (HINE) (Maydew House) works at an estimated value of £22m for an estimated period of 208 weeks from 21 August 2017 be approved.
2. That estimated internal fees of £651,200 and external fees of £1,577,000 making a total estimated scheme cost of £24,228,200 be noted.