Gateway 1: Peckham Rye station redevelopment procurement strategy

Meeting: 17/11/2015 - Cabinet (Item 12)

12 Gateway 1: Peckham Rye Station Redevelopment Procurement Strategy

To approve the procurement strategy for the Peckham Rye Station Square redevelopment construction.

Supporting documents:

Minutes:

RESOLVED:

 

1.  That the procurement strategy outlined in the report for the Peckham Rye Station Square redevelopment construction be approved. The procurement strategy will utilise the London Construction Programme framework at an estimated value of circa £6.2 million (based on the current cost plan) for the period of June 2016 to July 2018.

 

2.  That the use of single supplier negotiations for the retention of the feasibility design team (Landolt + Brown Architects, Sweett Group and Alan Baxter & Associates) through an extension to their existing contract be approved. This will be up to the point at which the construction contract is signed and the design team is either novated or replaced by the main contractor’s design team. The value of this appointment will not exceed £250,000 and will be based on the terms and fees outlined and procured for their initial appointment.