Decision Maker: Strategic Director of Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Approval of the variation to
extend the existing Housing Aids and Adaptations
Decision:
- That the variation of
Contract A for Housing Aids and Adaptation with Property Facilities
Group Ltd. (PFG), to extend the contract term by a maximum
additional period of five-months from 1 August 2026 to 31 December
2026 at an estimated additional cost of £350k making a total
revised estimated contract value of £2.721m, be
approved.
- That the variation of
Contract B for Housing Aids and Adaptation with Spokemead Maintenance Ltd. (Spokemead),
to extend the contract by a maximum additional period of
five-months from 1 August 2026 to 31 December 2026 at an estimated
additional cost of £300k making a total revised estimated
contract value of £2.365m, be approved.
- That
it be noted that the PFG and Spokemead
will act as backup contractors to each other on each of their
respective tendered rates, as required.
- That the annual Building Maintenance
Indices (BMI) rise, which was due in April 2026, will be applied to
both Contracts A and B contracts as agreed in principle with PFG
and Spokemead and is reflected in the
additional sums set out above, be noted.
Publication date: 28/08/2026
Date of decision: 27/08/2026
Effective from: 08/09/2026