Decision Maker: Strategic Director of Resources
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval of cost increase to main contract
That the Strategic Director of Finance:
1. Approves a variation to the works contract for the development at Slippers Place with Glenman Corporation Limited (Glenman) from £6,939,409 to £8,459,317 an increase cost of £1,519,908 for the reason noted in paragraphs 12-13 of the report.
2. Notes the revised total scheme costs from £8,548,562 to £10,576,082 including on-cost further details of which are in the closed report.
3. Notes a revised practical completion date of 5 December 2024.
4. Notes an additional variation to the capital programme in the sum of £1,674,694 is required for the reason noted in paragraphs 44-45 of the report.
Publication date: 13/02/2024
Date of decision: 08/02/2024
Effective from: 21/02/2024