Gateway 2 - Contract Award Approval for the Victory Community Park Landscape Construction works contract

Decision Maker: Acting Strategic Director of Environment, Sustainability and Leisure

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Gateway 2 Contract Award Approval for the Victory Community Park Landscape Construction works contract

Decision:

That the Strategic Director of Environment, Neighbourhoods and Growth approves:

1.  The award of the Victory Community Park landscape construction works contract to Blakedown Landscapes SE Ltd for a period of 22 weeks commencing 30 October 2023.

 

2.  The allocation of a client contingency to address the items identified in paragraph 40 of the report and delegates approval of expenditure of the contingency fund to the Director of Leisure.

 