Gateway 3 – Variation Decision: The Charter School East Dulwich Phase 2 demolition and strip out works

Decision Maker: Strategic Director of Children and Adult Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Contract variation approval

Decision:

That the Strategic Director of Children and Adult Services;

 

1.  Approves the variation of the contract with John F Hunt Regeneration Limited for demolition and enabling works for The Charter School East Dulwich Phase 2 by £887,402 excluding VAT for the additional costs to the end of June 2023.

 

2.  Approves the variation of the contract with John F Hunt Regeneration Limited for demolition and enabling works for The Charter School East Dulwich Phase 2 by £101,242 excluding VAT for security and scaffolding costs to the end of October 2023.

Publication date: 18/07/2023

Date of decision: 18/07/2023

Effective from: 26/07/2023