Decision details

Gateway 3 - Variation Decision for variations valued over £500,000 (Works) - Works Contract for the New Homes Delivery programme - Tissington Court

Decision Maker: Strategic Director of Housing

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval of cost increase to main works

Decision:

1.  That a variation to the works contract for the New Homes Delivery programme for Tissington Court with Guildmore Limited in the sum of £767,841.32 be approved, making a revised total contract value of £14,227,628.01.

 

2.  That it be noted that other additional works costs of £239,281.74 for the district heating, £7,313.51 for the gas enclosure and the increased associated on costs of £156,851.18 have been approved outside of this Gateway (GW) 3 approval, which following approval of recommendation 1 above will increase the total scheme costs to £17,193,403.00 representing an increase of 7.3% from the total scheme costs noted in the GW 3 approval of £16,022,115.00 on 19 January 2023.

Publication date: 16/05/2023

Date of decision: 15/05/2023

Effective from: 24/05/2023