Decision details

Gateway 2 - Contract Award Approval: Enabling works and demolition for Phase 1 of the Tustin Estate Low Rise

Decision Maker: Strategic Director of Housing

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

Contract award

Decision:

That the Managing Director of Southwark Construction, under the Strategic Director of Housing and Modernisation’s delegated authority:

 

1.  Approves the award of a contract to BY Development Ltd (trading as Linkcity) for enabling works and demolition for Phase 1 of the Tustin Estate Low Rise Redevelopment Programme in advance of entry into a Development Agreement for the estimated sum of£4.56m commencing on 29 July 2022 for an estimated period of three months.

 

2.  Notes that the above estimated sum includes a contingency sum in case of cost increases due to current market conditions, as set out in the closed report.

 

3.  Notes that the council intends to enter into a Development Agreement with BY Development Ltd (trading as

Urgent item?: Yes

Publication date: 28/07/2022

Date of decision: 27/07/2022