Decision details

Gateway 2 Styles House New Homes SE1

Decision Maker: Strategic Director of Housing

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Procurement strategy prior approval

Decision:

That the Strategic Director of Housing and Modernisation:

 

1.  Approves the award for the contract for Phase 1 of Styles House - a 2 -part contract for the enabling and demolition works contract (demolition, relocation of live boiler room, work on existing Styles House tower, utility works, and sub-station relocation) for the Styles House Estate project to Kind and Company Ltd for a fixed fee of £2.640m to commence contract mobilisation on the 11th July 2022.

 

2.  Note that the Phase 1 contract is split into two section with a break clause to be exercised in the event the land swap agreement with Transport for London (TfL) does not complete.

 

Section 1 – enabling works on LBS land only, pre land swap,

£870,000 (17 week programme)

Section 2 – enabling and demolition of LBS & TfL land, post land swap,

£1,770,000 (30 week programme)

 

  See Appendix A

 

3.  Approves the award of a Pre-construction Services Agreement (PSCA) to Kind and Company Ltd to develop an acceptable Contract Sum for construction for a fixed sum of £70k for a period of 24 weeks commencing on the 11th July 2022 with a target contract sum of £12.465m which will be subject to a separate Gateway 2 report approval in the future.

 

Publication date: 14/07/2022

Date of decision: 14/07/2022

Effective from: 22/07/2022

Accompanying Documents: