Decision Maker: Strategic Director of Finance and Governance
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Contract increase
1. That the variation to Commercial Way new build contract with Durkan Limited (Durkan) at an additional scheme cost of £4,836,486 be approved.
2. That it be inclusive of a variation to the contingency for the above contract to maintain a 5% build contingency.
3. That the reduction of £1,026,762 in the estimated on-costs associated with the contract be noted.
4. That the revised anticipated contract completion date of December 2023 be noted.
Publication date: 17/06/2021
Date of decision: 16/06/2021
Effective from: 25/06/2021