GW1 - Procurement Strategy for Design Services for the Tustin Estate Low Rise Redevelopment Programme

Decision Maker: Cabinet Member for Council Homes and Homelessness

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Procurement Strategy for Design Services for the Tustin Estate low-rise programme

Decision:

1.  That the Gateway 1 strategy to use the LHC Architect Design Services Framework (ADS) for the Tustin Estate Low Rise Re-development Programme to secure the design services of a design team with supporting specialist consultants at an estimated contract value of £2.5m for a period of 13 months commencing in August 2021, be approved.

 

2.  That the use of a resident-led interview panel in the procurement process as detailed in paragraphs 38-39 of the report, be noted.

 

Publication date: 21/05/2021

Date of decision: 21/05/2021

Effective from: 29/05/2021