Decision details

GW3 The Charter School East Dulwich Phase 2 - demolition contract variation for additional works

Decision Maker: Strategic Director of Children and Adult Services

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval to extend the demolition contract for The Charter School East Dulwich for additional works

Decision:

1.  That it be approved that the variation of the contract with John F Hunt Regeneration Limited for demolition and enabling works for The Charter School East Dulwich Phase 2 to increase the existing contract sum from £1,583,524 to £2,524,387 to include:

i) £687,532 for additional asbestos removal costs and.

ii) £253,331 to extend the scope of works to include soft strip works in the chateau.

 

2.   That it be noted that the council can reclaim the asbestos removal costs from the DfE as outlined in paragraph 21 of the report.

Publication date: 11/05/2021

Date of decision: 10/05/2021

Effective from: 19/05/2021