Decision Maker: Strategic Director of Children and Adult Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Contract award for the appointment of a contractor to carry out demolition and enabling works on the phase 2 site of The Charter School East Dulwich project to prepare it for the main works contract
1. That the award of the demolition and enabling contract for phase 2 of The Charter School East Dulwich project to John F Hunt Regeneration Limited in the sum of £1,589,524 consisting of £676,690 plus a provisional sum not to exceed £912,834 for asbestos removal costs be approved.
2. That a project contingency sum of £122,476 to meet any unforeseen costs be approved. This sum is the difference between the £1.712m approved at GW1 stage and £1,589,524.
3. That the decision to approve any spend against the project contingency sum be delegated to the Director of Education.
Publication date: 08/09/2020
Date of decision: 08/09/2020
Effective from: 16/09/2020