Gateway 3: Variation Decision – Extension to the Garages minor works and maintenance contract

Decision Maker: Strategic Director of Finance and Governance

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve an eighteen month extension to the contract

Decision:

That the contract extension of the garages minor works and maintenance contract (the contract) to PRB Estates Ltd (PRB) for a period of 18 months from 15 July 2020 to 31 January 2022 with a three month break clause at an estimated cost of £923,000 be approved.

 

Publication date: 03/07/2020

Date of decision: 03/07/2020

Effective from: 11/07/2020