Gateway 3: Contract variation in relation to Willow Walk and deed of settlement

Decision Maker: Strategic Director of Finance and Governance

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve a variation to the original contract for works at Willow Walk

Decision:

That the following be approved:

 

1.  The variation to Balfour Beatty Construction Ltd (‘Balfour Beatty’) for pre-construction services, early works and main works contracts in respect of the Willow Walk new temporary hostel accommodation and general needs housing project for a total variation of £1,156,761. This applies to each contract as follows:

 

2.  A variation to the contract with Balfour Beatty for pre-construction services (PCSA) relating to the Willow Walk new temporary hostel accommodation and general needs housing project. .

 

3.  A variation to the contract with Balfour Beatty for enabling works related to the Willow Walk new temporary hostel accommodation and general needs housing project.

 

4.  A variation to the contract with Balfour Beatty for main works related to the Willow Walk new temporary hostel accommodation and general needs housing project.

 

 

 

 

Publication date: 20/06/2019

Date of decision: 18/06/2019

Effective from: 28/06/2019