Gateway 3: Property and related insurances

Decision Maker: Strategic Director of Finance and Governance

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To agree the extension of the property insurance contract

Decision:

 

1.  That the extension of the property insurance and related insurances contract, with Zurich Insurance plc, trading as Zurich Municipal (ZMI), for a period of two years with effect from 1 October 2018 at an estimated annual value of £1,500,000 with a total extension value of £3,000,000 be approved.

 

2.  That it be noted that the strategic director of finance and governance will consider and approve any changes to the insurance coverage that may be offered as appropriate.

 

3.  That it be noted that the contract will be extended by way of deed of variation to the original contract.

 

 

Publication date: 21/06/2018

Date of decision: 20/06/2018

Effective from: 29/06/2018

Accompanying Documents: