To approve the award of contract

Decision:

1.  That the award of the contract to deliver construction of Pullens Gardens Redesign to the preferred contractor for a contract period of 16 weeks be approved.

 

2.  That the award of this contract with a client contingency of 9.5% be approved.

 

Publication date: 25/04/2017

Date of decision: 25/04/2017

Effective from: 04/05/2017