Decision details

Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contract

Decision Maker: Cabinet

Decision status: Information Only

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve cost of works to the Charter School East Dulwich (TCSED)

Decisions:

RESOLVED:

 

1.  That the award of the design and build contract for the Phase 1 works on Parcels 1 and 2 for The Charter School East Dulwich to Kier Construction Ltd for a contract period of approximately 72 calendar weeks commencing on 18 April 2017 and completing on 3 September 2018 be approved. 

 

2.  That a total expenditure of £25,325,000 for the works and associated costs with the phase 1 development be approved.

 

3.  That the award be subject to the council’s cost consultant’s final report being submitted confirming that this represents value for money and is approved by the strategic director of children’s and adults’ services prior to contract award.

Report author: David Quirke-Thornton

Publication date: 03/04/2017

Date of decision: 21/03/2017

Decided at meeting: 21/03/2017 - Cabinet

Effective from: 30/03/2017