Decision details

Southwark's Shopping Parade Capital Programme 2016-2018

Decision Maker: Cabinet Member for Regeneration and New Homes

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the sites for investment, the phasing of sites and allocation of funds

Decision:

That the cabinet member for regeneration and new homes:

 

1.  Agreed the selection criteria used to determine sites for shop front investments in the borough which is summarised in paragraphs 35-36 of the report, with the full criteria attached as appendix 1 to the report.

 

2.  Agreed the adoption of two programmes of shop front improvements, one at Peckham High Street / Rye Lane and the second across other key regeneration areas in the Borough, as set out in paragraphs 38-47 of the report.

 

3.  Agreed allocation of funding for these two programmes (paragraphs 54-58 of the report), site locations (paragraph 37 of the report and the map in Appendix 2 to the report) and the phasing of works (paragraphs 51-52 of the report).

Publication date: 10/02/2016

Date of decision: 10/02/2016

Effective from: 18/02/2016

Accompanying Documents: