Decision details

Financial Appraisal Process for Home Owners Affected by Regeneration Schemes

Decision Maker: Cabinet (decommissioned, for the Executive after 28 May 2026, please click the "Committees" tab on the right)

Decision status: Information Only

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

RESOLVED:

 

1.  That the revised process of financial appraisal to determine the appropriate re-housing support options for individual leaseholders affected by regeneration schemes be noted.

 

2.  That individual applicants should determine the application of their own savings towards their rehousing options be confirmed.

 

3.  That it be ensured that this approach is reflected in the delivery arrangements with development partners for new regeneration schemes, and that representations are made to existing development partners to seek their agreement to adopt the approach for current regeneration schemes.

Publication date: 09/12/2015

Date of decision: 08/12/2015

Decided at meeting: 08/12/2015 - Cabinet (decommissioned, for the Executive after 28 May 2026, please click the "Committees" tab on the right)

Effective from: 17/12/2015

Accompanying Documents: