Gateway 2: Contract Award Approval Camberwell Green Revitalise5 Main Contract

Decision Maker: Acting Strategic Director of Environment, Neighbourhoods and Growth

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the award of the Revitalise Camberwell Green contract

Decision:

1.  That the strategic director of environment and leisure approves the award of the Camberwell Green Revitalise main contract to Blakedown Landscapes SE Limited in the sum of £785,395.54, for a period of eight months.

 

2.  That the strategic director environment and leisure approves the allocation of a 10 per cent contingency totalling £78,540 which will be held within the project budget.

Publication date: 13/08/2015

Date of decision: 12/08/2015

Effective from: 22/08/2015