Decision details

Gateway 3 - Measured Term Contract for the Responsive Repairs and Planned Maintenance of Communal Lighting, Landlord’s Supplies and Lightning Protection

Decision Maker: Strategic Director of Finance and Corporate Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval of contract extension

Decision:

That the contract extension of the Communal Lighting and Lightning Protection contract to Spokemead Maintenance Ltd (Spokemead) for a period of 2 years from 1 October 2016 to 30 September 2018 at an estimated cost of £1.79m be approved.

 

Publication date: 08/07/2015

Date of decision: 30/06/2015

Effective from: 16/07/2015

Accompanying Documents: