Decision details

Gateway 3: Variation to the consolidated facilities management contract for 160 Tooley Street to include further operational buildings

Decision Maker: Strategic Director of Finance and Corporate Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the variation to the facilities management contract for Tooley Street to provide similar services at further operational buildings

Decision:

That the variation to the consolidated facilities management contract for 160 Tooley Street with Interserve Plc, namely to expand the operational scope to include the 25 additional buildings listed at Appendix 1 for the period 1 November 2014 to 31 January 2018 at an estimated annual cost of £1.29m giving a total estimated minimum value for this variation of £4m, in turn giving a revised total contract value of £18.7m for the initial term be approved.

 

Publication date: 01/09/2014

Date of decision: 29/08/2014

Effective from: 09/09/2014