Gateway 3: Variation decision: Coniston and Kevan precautionary fire proofing works

Decision Maker: Strategic Director of Finance and Corporate Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Variation of major works contract

Decision:

1.  That variation of the Coniston & Kevan Houses – Precautionary Fire Proofing Works contract with Standage & Co. Ltd for the works detailed in paragraphs 19 and 20 be approved.

 

2.  The additional external fees incurred be noted.

 

3.  That it be noted that further to paragraph 27 of the report there are scheme costs to the term door entry contractor (Silk & Mackman Services Ltd) and the term heating contractor (OCO Ltd) for enabling works.

 

4.  That the internal fees incurred on the scheme be noted.

 

5.  That the specific lessons learnt on this scheme which have been recorded and will be carried forward for future projects, both within the division (Major Works) and corporately (Appendix 1 of the report) be noted.

 

Publication date: 11/01/2013

Date of decision: 24/10/2012

Effective from: 01/11/2012