Decision Maker: Strategic Director of Resources
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Extension of the contracts for Lift Maintenance
1. That the variation of the Lift Maintenance Contract B (South) with Guideline Lift Services Ltd to extend the term of the contract for a period up to a maximum of nine months from 26 February 2024 to 25 November 2024 be retrospectively approved.
2. That an estimated additional sum of £1.377m with work added from Contract A (North) on their back-up tendered rates at an estimated additional sum of £1.243m making a total revised estimated contract value of £14.041m, be retrospectively approved.
Publication date: 31/07/2024
Date of decision: 30/07/2024
Effective from: 08/08/2024