Decision Maker: Strategic Director of Finance
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To approve the contract variation
1. That the variation to Aylesbury FDS B works contract with Hill Partnerships Ltd by £2,118,326, be approved.
2. That the revised total scheme cost inclusive of a works costs variance and the addition of a contingency sum as further detailed in the closed report, be approved.
3. That the revised anticipated contract completion date of August 2025, be noted.
Publication date: 23/05/2023
Date of decision: 22/05/2023
Effective from: 01/06/2023