Decision details

Gateway 3 – Variation Decision Aylesbury FDS B

Decision Maker: Strategic Director, Finance

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the contract variation

Decision:

 

 

1.  That the variation to Aylesbury FDS B works contract with Hill Partnerships Ltd by £2,118,326, be approved.

 

2.  That the revised total scheme cost inclusive of a works costs variance and the addition of a contingency sum as further detailed in the closed report, be approved.

 

3.  That the revised anticipated contract completion date of August 2025, be noted.

 

Publication date: 23/05/2023

Date of decision: 22/05/2023

Date comes into force if not called in: 01/06/2023

Call-in deadline date: 31/05/2023

Current call-in Count: 0

Accompanying Documents: