Approval for variation for cost increase.

Decision:

That the Strategic Director of Housing:

 

1.  Formalises his approval of the variation to the Temporary Accommodation Contract 1, refurbishment/conversion contract with Niblock (Builders) Limited (Niblock), varying the contract sum from £2,086,229 to £2,647,251, an increase of £561,022.

 

2.  Approves a variation to the contingency for the above contract, increasing the contingency from £104,311 to £132,363, an increase of £28,052.

 

3.  Notes the increase to estimated on-costs, including a 4% development allowance associated with the contract, as a result of the above requested approvals from £371,138 to £403,065 an increase of £31,927.

 

4.  Notes the increase of the total scheme costs from £2,561,678 to £3,182,679 resulting to a total scheme variation of £621,001.

 

5.  Notes that this report was considered at the Departmental Contract Review Board (DCRB) in July 2022 but was not sent for approval until May 2023.

 