Decision Maker: Strategic Director of Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval to procure services of demolition contractor - paper to include tender report and total scheme costs update.
1. That the award of the Bromyard House demolition contract, as part of Phase 1 of the Ledbury Estate redevelopment, to Coleman and Company Limited procured from ProcurePublic Ltd’s Demolition framework for a period of 33 weeks commencing on 24 October 2022 for the sum and total contract value of £1,198,214 be approved.
2. That it be noted that that this scheme will benefit from £100,000 per unit grant subsidy from the Greater London Authority, which results in a total contribution of £26m.
Publication date: 19/10/2022
Date of decision: 18/10/2022
Effective from: 27/10/2022